Orthos projects employs citectSCADA
UK company, Orthos Projects has successfully completed a turnkey contract to design and build a new state- of- the- art Greensand preparation plant, part of a complete new casting facility for Scaw Metals, South Africa's leading producer of high chrome grinding media for the mining industry. The turnkey project, part of Scaw's multi-million Rand expansion programme in its high chrome foundry, employs a CitectSCADA system to provide plant visualisation and operator interface. In addition, the Citect system has a modem connection allowing remote observation, fault diagnosis and troubleshooting by Orthos technical staff from anywhere in the world.
'We have used CitectSCADA successfully on several of our international foundry projects,' said Alan Piper, Project Engineer for Orthos Projects.
'It is an extremely fast and easy-to use system'.
'We like the way it enables us to do just what we need to do, even down to data logging, and the way it expands easily and flexibly as the requirements of our customers grow'.
'A major benefit is that we do not need to purchase development licences for CitectSCADA.
This reduces our costs substantially, and also helps our clients, who can make changes to their systems without the added cost of a development system'.
The Scaw Metals project consolidates Orthos Projects growing reputation within the South African marketplace.
It required Orthos to design and install a new state-of-the-art 45tph Greensand preparation plant, as part of a complete new casting facility.
Greensand plants are systems used in many foundries for the production of cast iron assemblies.
They employ moulds made from a number of materials, primarily sand; hence, there is a need for systems to produce this sand automatically.
New raw materials (typically silica sand, clay, coal dust and water) are weighed and mixed with old, already- used sand in order to provide the ideal 'green sand' for a molding machine.
A mixer is used to combine all these materials, typically mixing around 4 tons at a time.
Finally, a molding machine is responsible for shaping and squeezing the sand, ready for the molten metal to be added.
The specification for the Greensand plant supplied to Scaw Metals demanded the very latest high technology, energy efficient equipment, with integrated computer, PLC and SCADA control systems.
However, with over 25 years experience in foundry engineering Orthos Projects proved that they had the technical merit, track record and innovative capability to produce the exact specification of sand plant required.
The plant was engineered in the UK and was supplied complete with all key components.
This factor, combined with a local supply for structural steelwork and construction labour, enabled an extremely quick project turnround of just over 9- months from order placing to first production.
A new tower building houses the 45tph sand preparation plant capable of supplying the Disamatic moulding machines requirements, incorporated within the plant is an Eirich intensive batch mixer chosen for its high degree of sand preparation, reliability and low maintenance.